Splash Pad Project
Splash Pad Project Costs:
Project Quote
$ 370,000
Admin Cost Estimate
8,000
Total Project Cost $ 378,000
Amount Raised To Date
( 45,373)
Donations to be Raised $ 332,627
Brick Order Form - Loyal Splash Pad
Loyal Splash Pad Donor Envelope
Link to “Order a Brick” Form
Project Description:
• Construct a 2500 square foot concrete Splash Pad at the City of Loyal WI
Westside Park
Recirculating Water Flow design – Total Cost – VORTEX = $370,000.
The City can opt to have local vendor / contractors provide Concrete, Electrical,
Site Restoration and Excavation.
Total In-Kind Donation Options = $82,000.
Net Contract with VORTEX is $288,000 (including Water Features)
Splash Pad Project
Features and Project Plan
Loyal Splash Pad Donor Commitment Agreement
SPONSORED